County: Sedgwick Select location of well to view details. Click on column heading to sort. |
![]() |
![]() |
View page: < Prev || 111 || 112 || 113 || 114 || 115 || 116 || 117 || 118 || 119 || 120 || Next > | |||||||||
T-R-S | Owner | Well Depth Ascend. Desc. |
Static Water Level Ascend. Desc. |
Est. Yield Ascend. Desc. |
Well Use | Other ID | Action Taken | Completion Date Ascend. Desc. |
Scan? |
T26S, R1E, Sec. 29 NW NW NE |
Paquette, Ray | 47 ft. | 20 ft. | 40 gpm. | Domestic, Lawn and Garden | Constructed | 08-Aug-2012 | ||
T26S, R1E, Sec. 29 NW NW SW |
Patterson, Mike | 36 ft. | 12 ft. | 20 gpm. | Domestic, Lawn and Garden | Constructed | 09-Jan-2002 | ||
T26S, R1E, Sec. 29 NW NW SW |
Patterson, Mike | 36 ft. | 12 ft. | Domestic, Lawn and Garden | Plugged | 09-Jan-2002 | |||
T26S, R1E, Sec. 29 NW SW NW |
Patterson, Mike | 30 ft. | 10 ft. | Domestic | Plugged | 14-Sep-1995 | |||
T26S, R1E, Sec. 29 SW SW NW |
Patterson, Mike | 43 ft. | 13 ft. | 30 gpm. | Domestic | Constructed | 01-Jan-1995 | ||
T26S, R1E, Sec. 29 NW SW NW |
Patterson, Mike | 32 ft. | 13 ft. | 30 gpm. | Domestic | Constructed | 15-Sep-1995 | ||
T26S, R1E, Sec. 29 NW NE NE |
Phillips | 38 ft. | 18 ft. | Domestic, Lawn and Garden | Constructed | 16-Jun-2015 | |||
T26S, R1E, Sec. 29 NW NW SW NW |
Piland, Greg | 50 ft. | 10 ft. | Domestic, Lawn and Garden | Constructed | 06-Oct-1999 | |||
T26S, R1E, Sec. 29 SE SW SW SE |
Pittsenberger, John | 42 ft. | 18 ft. | 50 gpm. | Domestic | Constructed | 05-Nov-1988 | ||
T26S, R1E, Sec. 29 SW SW NE |
Poelma, Bill | 30 ft. | 15 ft. | Domestic | Constructed | 22-Jul-1987 | |||
T26S, R1E, Sec. 29 SW NW NE |
Pruitt, Jr. | 40 ft. | 15 ft. | Domestic, Lawn and Garden | Constructed | 18-Jun-1981 | |||
T26S, R1E, Sec. 29 NE SW SE |
Rankin Enterprises | 45 ft. | 17 ft. | Domestic | Constructed | 01-May-1981 | |||
T26S, R1E, Sec. 29 SW SW SW SE |
Rankin Enterprises | 40 ft. | 15 ft. | Domestic | Constructed | 12-Dec-1980 | |||
T26S, R1E, Sec. 29 NE SW NE |
Renello, Joyce | 17 ft. | 10 ft. | Domestic, Lawn and Garden | Plugged | 16-Oct-1999 | |||
T26S, R1E, Sec. 29 NW SE SW SE |
Richard Weir Construction | 40 ft. | 12 ft. | Domestic | Constructed | 04-Aug-1980 | |||
T26S, R1E, Sec. 29 SW SW SE |
Richard Weir Construction | 40 ft. | 18 ft. | Domestic | Constructed | 24-Oct-1980 | |||
T26S, R1E, Sec. 29 SW NW SW SE |
Richard Weir Construction | 40 ft. | 12 ft. | Domestic | Constructed | 01-Jul-1980 | |||
T26S, R1E, Sec. 29 SW NW SW SE |
Richard Weir Construction | 42 ft. | 15 ft. | Domestic | Constructed | 06-Jan-1981 | |||
T26S, R1E, Sec. 29 SW SW SE |
Richard Weir Construction | 45 ft. | 15 ft. | Domestic | Constructed | 27-Jan-1981 | |||
T26S, R1E, Sec. 29 SW NW SW SE |
Richard Weir Construction | 26 ft. | 12 ft. | 48 gpm. | Domestic | Constructed | 06-Jun-1980 | ||
T26S, R1E, Sec. 29 SE SE SW |
Richard Weir Construction | 40 ft. | 15 ft. | Domestic | Constructed | 30-Jun-1982 | |||
T26S, R1E, Sec. 29 NW SW SW SE |
Richard Weir Construction | 40 ft. | 15 ft. | Domestic | Constructed | 27-Feb-1982 | |||
T26S, R1E, Sec. 29 SW SW NE NE |
Richards, Cecil | 40 ft. | 15 ft. | Domestic | Constructed | 12-Feb-1990 | |||
T26S, R1E, Sec. 29 SW NW NW |
Ripley Power Plant | 40 ft. | 15 ft. | Domestic | Constructed | 25-Aug-1997 | |||
T26S, R1E, Sec. 29 NW SW NE |
Rush, Kit | 36 ft. | 7 ft. | Domestic | Constructed | 21-Aug-1993 | |||
T26S, R1E, Sec. 29 NW NW NE NE |
Schultz, Ben | 20 ft. | 10 ft. | 50 gpm. | Domestic | Constructed | 02-Mar-1978 | ||
T26S, R1E, Sec. 29 NE SW NE |
Simkins, Bruce | 40 ft. | 17 ft. | 35 gpm. | Domestic | Constructed | 09-Jun-1977 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 24 ft. | Monitoring well/observation/piezometer | MW 3 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 18 ft. | Monitoring well/observation/piezometer | MW E | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | Monitoring well/observation/piezometer | MW 5 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NW SW SE |
Southwestern Bell | 20 ft. | Monitoring well/observation/piezometer | MW 8 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NW SW SE |
Southwestern Bell | 20 ft. | Monitoring well/observation/piezometer | MW F | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | Monitoring well/observation/piezometer | MW 1 | Plugged | 17-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | Monitoring well/observation/piezometer | MW 7 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 20 ft. | Monitoring well/observation/piezometer | MW D | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 21.5 ft. | Monitoring well/observation/piezometer | MW 4 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 20 ft. | 14 ft. | Monitoring well/observation/piezometer | MW D | Constructed | 18-Aug-1992 | ||
T26S, R1E, Sec. 29 NW SE SW |
Southwestern Bell | 21 ft. | 15.67 ft. | Monitoring well/observation/piezometer | MW 3 | Constructed | 22-Apr-1991 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | Monitoring well/observation/piezometer | MW 6 | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | Monitoring well/observation/piezometer | MW B | Plugged | 18-Dec-2001 | |||
T26S, R1E, Sec. 29 NW SW SE |
Southwestern Bell | 20 ft. | 14 ft. | Monitoring well/observation/piezometer | MW F | Constructed | 19-Aug-1992 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22.5 ft. | 12.8 ft. | Monitoring well/observation/piezometer | MW 7 | Constructed | 01-Sep-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22.5 ft. | 15.6 ft. | Monitoring well/observation/piezometer | MW 8 | Constructed | 19-Oct-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | 17.1 ft. | Monitoring well/observation/piezometer | MW 1 | Constructed | 20-Mar-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 20 ft. | 17.1 ft. | Monitoring well/observation/piezometer | Constructed | 28-Feb-1991 | |||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | 14.6 ft. | Monitoring well/observation/piezometer | MW 4 | Constructed | 13-Jun-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 24.5 ft. | 16.7 ft. | Monitoring well/observation/piezometer | MW 2 | Constructed | 17-May-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 22 ft. | 14.6 ft. | Monitoring well/observation/piezometer | MW 5 | Constructed | 13-Jun-1989 | ||
T26S, R1E, Sec. 29 NE SE SW |
Southwestern Bell | 26 ft. | 15 ft. | Environmental Remediation, Recovery | RW | Constructed | 18-Oct-1993 | ||
T26S, R1E, Sec. 29 NW SE SW |
Southwestern Bell | 22 ft. | 16.3 ft. | Monitoring well/observation/piezometer | MW 2 | Constructed | 22-Apr-1991 | ||
View page: < Prev || 111 || 112 || 113 || 114 || 115 || 116 || 117 || 118 || 119 || 120 || Next > |